11. In MTO planning strategy, finish products are not produced until you receive sales order from a customer?
A. True
B. False
Answer : A

12. Which of the following doesn’t represent an issue Material Requirement Planning element?
A. Sales Order
B. PIR
C. Transfer Order
D. Production Order
Answer : D

13. Which of the following transaction code is used to create Planned Independent Requirement PIR?
A. MD61
B. MD62
C. MD04
D. MD05
Answer : A

14. You can create a Production order from?
A. Directly from Stock Requirement List
B. Using Planned Order
C. Both of these
Answer : C

15. Material master contains data related to scheduling, capacity planning and production costing?
A. True
B. False
Answer : B